用 NETWORKDAYS(开始, 结束, 节假日范围) 统计起止日之间的工作日。默认周末是周六和周日;起止当天如果是工作日,会计入结果。2026-11-03 至 2026-12-11 不含节假日是 29 天;把 11 月 26 日感恩节列入节假日列表后是 28 天。

本文目录

快速解答

用 NETWORKDAYS(开始, 结束, 节假日范围) 统计起止日之间的工作日。默认周末是周六和周日;起止当天如果是工作日,会计入结果。2026-11-03 至 2026-12-11 不含节假日是 29 天;把 11 月 26 日感恩节列入节假日列表后是 28 天。

=NETWORKDAYS(A2, B2, Holidays!A2:A)

检查要点

周末不是周六日时,改用 NETWORKDAYS.INTL。周五和周六休息可用周末代码 7,或文本字符串 "0000110"(从周一开始的 7 位,1 表示休息日)。同一段日期、无节假日时结果是 28。输入 0000110 时不要让它变成数字 110,否则会出现 #NUM!。

边界与兼容性

起止日相同且为工作日时结果是 1,若当天是周末或节假日则是 0。开始日期晚于结束日期时,Sheets 返回负数而不是报错。落在周末的节假日不会再被多减一次。要推算几个工作日之后的日期,用 WORKDAY 或 WORKDAY.INTL;开始当天本身不计入。以上结果于 2026 年 11 月 12 日在 Google Sheets 中实测。

完整英文示例、公式与作者备注

Tested in: Live formula checks in Google Sheets on 12 November 2026. Results below come from those checks. I did not re-run the same workbook in Excel for this article; Excel has functions with the same names and argument order, but the counts here should be read as Sheets results.

Which versions this applies to

Google Sheets on the web and in the mobile apps. NETWORKDAYS and NETWORKDAYS.INTL also exist in current Excel; I did not verify the menu steps or the results in Excel this time.

Dates in the examples are real date values, not text that happens to look like a date. If a formula returns #VALUE! or a count that is clearly too low, check dates stored as text first.

A concrete booking

A contractor is booked from Tuesday 3 November 2026 through Friday 11 December 2026 and bills only weekdays. Put 2026-11-03 in A2 and 2026-12-11 in B2:

=NETWORKDAYS(A2, B2)

That returned 29. Thanksgiving in the United States falls on Thursday 26 November 2026 in this year. After adding that single date to a holiday list (the next step), the same range returned 28.

Those two numbers are the ones the rest of this tutorial keeps coming back to.

Step 1: Count Monday–Friday with NETWORKDAYS

NETWORKDAYS treats Saturday and Sunday as the weekend. It counts every other day in the range, including the start and the end when those days are weekdays.

A short week makes the inclusive rule obvious:

StartEndFormulaResultWhy
Mon 9 Nov 2026Fri 13 Nov 2026=NETWORKDAYS(A2, B2)5Five weekdays, both ends included
Mon 9 Nov 2026Sun 15 Nov 2026same5Saturday and Sunday add nothing
Thu 12 Nov 2026Thu 12 Nov 2026same1A single weekday counts as one day
Sat 14 Nov 2026Sat 14 Nov 2026same0A single weekend day counts as zero

If you only needed a Monday–Friday count and had no holidays, you could stop here. Most invoices and project plans need at least one public holiday taken out.

Step 2: Keep holidays on their own sheet

Create a sheet named Holidays. Put a header in A1 and the dates starting in A2. One column is enough; a note in column B is optional.

For the checks in this article the list was:

AB
1HolidayNote
22026-11-26US Thanksgiving (Thu)
32026-12-25Christmas (Fri)
42026-11-28A Saturday, used only as a test
52026-11-11Veterans Day (Wed)

Point NETWORKDAYS at that column. A2:A works, and so does a bounded range such as A2:A20. Extra blank cells at the bottom did not change the counts I got.

=NETWORKDAYS(A2, B2, Holidays!A2:A)

On the contractor booking (3 Nov to 11 Dec) this returned 28, because 26 November is inside the range and 25 December is not. Christmas is on the list for later use; it does not affect this particular booking.

A holiday that falls on a Saturday is not subtracted twice. The week from Monday 23 November to Sunday 29 November contains Thanksgiving (Thursday) and the Saturday test holiday:

  • =NETWORKDAYS(A2, B2) returned 5
  • =NETWORKDAYS(A2, B2, Holidays!A2:A) returned 4

Only the Thursday came off. The Saturday was already a weekend.

Two other checks from the same list:

  • Monday 9 November to Friday 13 November, with Veterans Day on Wednesday the 11th, returned 4.
  • A start and end that are both Thanksgiving returned 0. A start on Thanksgiving and an end on Friday 27 November returned 1 — only the Friday counts.

Step 3: Change the weekend with NETWORKDAYS.INTL

NETWORKDAYS will not help if the team works Sunday to Thursday, or if only Sunday is off. NETWORKDAYS.INTL adds a weekend argument before the holiday list:

=NETWORKDAYS.INTL(A2, B2, 7, Holidays!A2:A)

Weekend argument 1 is Saturday and Sunday, the same rule as NETWORKDAYS. On the Thanksgiving week (Mon 23 Nov to Fri 27 Nov) both of these returned 4:

=NETWORKDAYS(A2, B2, Holidays!A2:A)
=NETWORKDAYS.INTL(A2, B2, 1, Holidays!A2:A)

Weekend argument 7 is Friday and Saturday. For Sunday 8 November through Saturday 14 November, with no holidays, that returned 5 — Sunday through Thursday.

The same weekend can be written as a string of seven 0s and 1s that starts on Monday. A 1 marks a weekend day. Friday and Saturday are the fifth and sixth characters:

=NETWORKDAYS.INTL(A2, B2, "0000110")

On that same 8–14 November range, the string also returned 5. If you type 0000110 into a cell and Sheets stores it as the number 110, the formula returns #NUM!. Keep the value as text (type an apostrophe before the digits, or wrap it in quotes inside the formula).

I also checked weekend code 11 (Sunday only) on 8–14 November: the result was 6, Monday through Saturday.

I did not run every other weekend code. For a pattern I have not tested, the seven-character string is easier to inspect than a code number: a 1 in a position means that day is a weekend, starting at Monday.

Back to the contractor booking, Friday–Saturday weekend, no holidays:

=NETWORKDAYS.INTL(A2, B2, 7)

That returned 28. And Thanksgiving week with weekend 7 plus the holiday list returned 3: Monday, Tuesday and Wednesday. Friday is already a weekend in this system, and Thursday is the holiday.

Step 4: Find a date n working days later with WORKDAY

NETWORKDAYS counts the days between two dates. WORKDAY (and WORKDAY.INTL) starts at a date and moves forward a number of working days. The start date itself is not one of those days.

Three working days after Monday 23 November 2026, skipping Thanksgiving:

=WORKDAY(A2, 3, Holidays!A2:A)

The result was Friday 27 November 2026 — Tuesday, Wednesday, then Friday.

WORKDAY.INTL takes the same weekend codes. Three working days after Sunday 8 November, with weekend 7 (Friday and Saturday off; Sunday is a workday), returned Wednesday 11 November. Sunday is the start, so it is not counted; the three days are Monday, Tuesday and Wednesday.

If the start falls on a weekend, WORKDAY skips to the next working day and then counts from there. One working day after Saturday 14 November 2026 returned Monday 16 November.

When the start is after the end

I ran =NETWORKDAYS(DATE(2026,11,13), DATE(2026,11,9)) — Friday back to the preceding Monday. Sheets returned -5, not an error. If you might paste dates in either order, wrap the call in a check rather than assuming a negative count will be noticed:

=IF(B2<A2, "Start is after end", NETWORKDAYS(A2, B2, Holidays!A2:A))

Common mistakes

Typing 0000110 as a weekend code and letting Sheets treat it as 110, which raises #NUM!. Force it to text, or use weekend code 7 instead.

Using NETWORKDAYS for a Friday–Saturday weekend. The count will look almost right and still be wrong; switch to NETWORKDAYS.INTL.

Assuming a holiday that lands on Saturday will take another day off the Monday–Friday count. It won’t.

Expecting WORKDAY’s start date to be included in the n days. It is the date you start from, not day one of the count.

Feeding the functions text that looks like a date. Fix the cells first; the dates stored as text tutorial covers the usual repairs.

FAQ

Does NETWORKDAYS count the start date and the end date?

Yes, when those dates are working days. Thursday 12 November 2026 to itself returned 1. The same formula on Saturday 14 November returned 0.

How do I count working days if Friday and Saturday are the weekend?

Use NETWORKDAYS.INTL with weekend argument 7, or with the text string "0000110". On 8–14 November 2026 both forms returned 5.

What happens if the start date is later than the end date?

In the Sheets check, NETWORKDAYS returned a negative number (−5 for 13 November back to 9 November). It did not throw an error.

How do I get the date n working days after a start date?

WORKDAY for a Saturday–Sunday weekend, WORKDAY.INTL for any other weekend. Three working days after 23 November 2026, excluding Thanksgiving, was 27 November 2026.

Can I use these formulas in Excel?

Excel provides NETWORKDAYS, NETWORKDAYS.INTL, WORKDAY and WORKDAY.INTL with the same argument order. The figures in this article come from Google Sheets on 12 November 2026 and were not retested in Excel here.

Live-test findings

All counts in the tables and examples were entered in a private Google Sheet on 12 November 2026 and read back from the calculated cells. I did not test every NETWORKDAYS.INTL weekend code; the ones I ran were 1, 7, 11, and the string "0000110". Locale-specific date parsing and semicolon argument separators were not part of this check.

Sources

  • Google Sheets function list for NETWORKDAYS, NETWORKDAYS.INTL, WORKDAY and WORKDAY.INTL, used for argument order and the meaning of weekend codes 1, 7 and 11. The counts themselves come from the 12 November 2026 workbook, not from the documentation examples.
Oscar

专注电子表格公式与排错;具体测试环境和待验证事项见各篇文章。

Tested in Google Sheets, 12 November 2026.

本主题下一篇:日期与时间 Google Sheets 日期与时间公式速查